A new labour study warns that skills shortages and retention risk could constrain England's five year investment plan.
2 Aug 2026

There is a curious mismatch at the heart of Britain's water investment boom. The industry has money, 104 billion pounds of it under AMP8, but not necessarily the people to spend it well. Recruitment specialist Murray McIntosh has launched the 2026 edition of its Water Industry Labour Report, calling on professionals across the sector to share their experiences at what it calls a pivotal moment for delivery.
Over successive editions, the report has become one of the more widely cited workforce assessments in the sector. Previous rounds shaped strategic workforce planning across major frameworks and fed into recommendations from the Independent Water Commission's review of the industry. This year's version pushes further, examining workforce wellbeing and the role artificial intelligence might play in easing productivity pressures.
Money alone cannot fix a sector under this kind of strain, and the expanded remit reflects that. Workload pressures and workplace culture, the study finds, are already shaping retention and performance. Attitudes toward automation, too, are shifting, though not always in a direction that eases anxiety about job security.
Adam Cave, Director at Murray McIntosh, argued that understanding frontline experience has never mattered more as AMP8 gathers pace. The industry's challenges, he said, cannot be solved without listening to those doing the work. His framing was pointed: insight built from engineers and delivery professionals, not top down commentary.
None of this concern is new, nor confined to one report. Specialist recruiters have warned this year that early AMP8 delivery delays partly reflect resourcing constraints rather than purely technical or financial ones. Previous editions of the same labour report found nearly half of engineers cite skills shortages as their biggest challenge, with a meaningful share weighing an exit from the sector altogether.
Drainage and sewer capacity programmes illustrate the stakes most sharply. Delivery there increasingly depends on scarce specialist skills in hydraulics, digital monitoring and sustainable drainage design, precisely the kind of expertise that takes years to build and little time to lose.
Capital commitments, in other words, only travel as fast as the workforce behind them. Whether AMP8 delivers on schedule may hinge less on funding levels than on whether the sector can hold onto the engineers already doing the job.